Gas Processing Facility “Arystan Oilfield”, “Ken-Sary” LLP

Gas Processing Facility “Arystan Oilfield”, “Ken-Sary” LLP

More>

Unit brief description:

  • Unit Purpose:                                            Gas utilization and LPG production;
  • Construction beginning date:                 August 2013;
  • Unit Startup date:                                     July 2014;
  • Unit Total Capacity:                                  150 million Nm3/year;
  • Feed gas:                                                     Associated Gas;
  • Dehydration principle:                             Low temperature separation with inhibitor injection;
  • Fractionating principle:                            Stabilization;
  • Working pressure:                                      5.5 MPa;
  • Main products:                                           LPG, Dry Natural Gas;
  • Other products:                                          Fuel gas, condensate, nitrogen, instrument air;

 

 

Brief description of scope of work:

Our company has performed the following scope of work:

  • Technology development;
  • Equipment supply;
  • Logistics;
  • Construction work supervision;
  • Commissioning;
  • Personnel training;
  • Entire Unit startup;
  • Technical service for 1 year;
  • Warranty for 2 years for all supplied equipment..